Jul 01, 2024 Leave a message

Progress Of Large Central Air Conditioning Production Base Project

Progress of Large Central Air Conditioning Production Base Project

 

The Xiongguan Road is like iron, and the second phase of construction is non-stop. After the start of spring, the construction team's various projects are in full swing, and the current progress of the project is as follows:


1. The insulation and waterproofing construction of the exterior walls in the framework building area has been completed, and the paint construction is nearing completion. The leveling work for floors 2-4 has been completed, and the waterproofing layer, isolation layer, and fine stone concrete layer are about to start on the roof;
2. The installation of columns, beams, and connectors in the southern section of the steel structure area has been completed. Three QD type double beam cranes have been installed and tested for power on, and the repair work of fireproof coatings is about to end.
The next project schedule is as follows:
1. The finishing work for the roof and exterior walls of the frame building will take about 15 days;
2. The installation period for roof tiles in the steel structure area is about 10 days, the installation period for wall tiles is about 25 days, and the construction period for the factory floor is about 7 days.
 

news-546-302

news-545-301

 

Lithium bromide solution manufacturer

 

About us

Flier Refrigeration Engineering Technology Co., Ltd is a professional technical service enterprise integrating central air-conditioning host sales, spare parts sales, unit repair and maintenance.

Factory located in Zhenjiang, Jiangsu, covering an area of 25,000 square meters ,and has been built with 1 R&D center, 1 pilot plant, 3 An innovative production, learning, and research base composed of a professional production workshop and its corresponding infrastructure. At present, the company has become a well-known technical service provider in the field of central air conditioning in China.

The company's main business scope includes: central air-conditioning maintenance, cleaning and technical services; cooling tower and fan coil cleaning and maintenance services; custom processing of lithium bromide solution; sales of lithium bromide solution special impurity separators; central air-conditioning host and various zero Sales of accessories; installation and sales of central air conditioning systems, etc.

20230613164954-1

Contact us

Ms. Lillian GUO

Zhenjiang FLIER Refrigeration Engineering Technology Co., Ltd

Jiangsu, China

Tel: + 86 15358588768(Whatsapp)

Wechat:15358588768

E-mail: mdguolijuan@zjflier.com

 

Send Inquiry

whatsapp

Phone

E-mail

Inquiry